Original Project Due Date

rated by 0 users
Not Answered This post has 0 verified answers | 3 Replies | 2 Followers

Not Ranked
3 Posts
Points 49
Maria posted on Wed, Feb 3 2010 3:29 PM

Hi,

I am currently configuring the Portfolio DashBoard List and wonders what the difference between the two fields "Original Project Due Date" and "Baseline End Date" is?

Could you elaborate a bit about the purpose of "Original Project Due Date" please.

Thanks,

Maria

All Replies

Top 10 Contributor
239 Posts
Points 3,409

Hello Maria,

"Original Project Due Date" is your planned date/targeted date, i.e. it's not your Actual Due Date. When your project is finalized and at that point you want to take the snapshot of all the data (budget, cost...etc.) that would be the "Baseline End Date".

Product Team

 

Not Ranked
3 Posts
Points 49
Maria replied on Thu, Feb 4 2010 3:45 AM

Hi,

thanks for your reply!

Still, this makes me a bit confused. The "Baseline End Date" I do understand and obviously "Actual End Date". However, to me planned date/targeted date would be the field "Forecasted End Date" or maybe "Current Project Due Date". "Original Project Due Date" sounds to me a due date that was set in the beginning of the project, i.e. the same as "Baseline End Date".

Could you just briefly exaplain the differences and purpose regarding all these end dates:

  1. Actual End Date
  2. Baseline End Date
  3. Forecasted End Date
  4. Original Project Due Date
  5. Current Project Due Date

Best regards,

Maria

Top 10 Contributor
239 Posts
Points 3,409

We defined the terms similar to the reference here:

http://www.project-management-knowledge.com/definitions/p/planned-finish-date/

  • Scheduled Finish Date (SF) In project management, Scheduled Finish date (SF) or planned finish date, is the date and time work was scheduled to...  
  • Finish Date The term finish date refers specifically to the date in which the particular schedule activity as part of the overall...  
  • Baseline Finish Date  The term baseline finish date applies to the date on which a schedule activity is expected to be completed...  
  • Planned Start Date See scheduled start This term is defined in the 3rd edition of the PMBOK but not in the 4th. ...  
  • Current Finish Date The term current start date refers to the deliberate and calculated estimate of the specific point in time at which...
  • In our app, we use "Original Project Due Date" instead of "Scheduled Finish Date" and "Current Project Due Date" instead of "Current Finish Date". They are there so you can associate them with AC, PV, BAC, EAC...etc.

    Here're the fields:

    Where is the data stored?

    We provide a list template with the web part so users will have a Bamboo Project Dashboard list on the site where they deploy the web part. The Bamboo Project Dashboard list has the following columns:

     

    1. Project Name – Single line of text
    2. Project Manager – People/Groups
    3. Project ID – Single line of text.
    4. Project Status – Choice field with the choices shown below saved as Single line of text. These choices can be modified by the customer since we don’t expect them to be any particular value.
      1. Active
      2. Complete
      3. Cancelled
      4. Pending
    5. Project Type - Choice field with the choices shown below saved as Single line of text. These choices can be modified by the customer since we don’t expect them to be any particular value.
      1. Custom
      2. Marketing
      3. Product
      4. Other
    6. Project Phase - Choice field with the choices shown below saved as Single line of text. These choices can be modified by the customer since we don’t expect them to be any particular value.
      1. Initiating
      2. Planning
      3. Executing
      4. Controlling
      5. Closing
    7. Executive Summary – Multi-line of text field. This is a place for the user to write a short project charter, report/summary or list issues/risks.
    8. Issue Description. Single line of text describing main issue affecting overall status of the project.
    9. Baseline Start DateDate Field that stores just date (not time). User manually enters the value.
    10. Baseline End Date – Date Field that stores just date (not time). User manually enters the value.
    11. Actual Start Date – Date Field that stores just date (not time). User manually enters the value.
    12. Actual End Date – Date Field that stores just date (not time). User manually enters the value.
    13. Forecasted End Date - Date Field that stores just date (not time). User manually enters the value.
    14. Project Completion (Percentile) – User manually enters the % value.
    15. Duration – User manually enters the value. There is another field for duration (see #x) that we calculate.
    16. Original  Project Due Date – User manually enter the value
    17. Current Project Due Date –– User manually enter the value
    18. Project Original Budget (BAC) – User manually enters the value ($). Must be a number because we will use it to calculate EAC (see below).
    19. Project Current Expense (AC) – User manually enters the value. Must be a number because we will use it to calculate CV and CPI (see below).
    20. Project Planned Expense (PV) – User manually enters the value. Must be a number because we will use it to calculate SV and (see below).
    21. Project Earned Value (EV) – User manually enters the value. Must be a number because we will use it to calculate CV, SV, CPI, and SPI (see below).
    22. Project Health Overall Status (on-track, delayed, stop…etc) – User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value.
    23. Project Health Schedule Variance Status (on-track, early, late…etc) – User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value. There is a similar field that is calculated.
    24. Project Health Effort Variance Status (on-track, under, over…etc) – User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value.
    25. Project Health Cost Variance Status (on-track, under, over…etc) – User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value.
    26. Project Scope Variance Status (scope creep, cannot implement one of the requirements…etc.) – User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value.
    27. Project Health Customer Feedback Status (normal, under, over…etc) - User selects from a choice field. These choices can be modified by the customer since we don’t expect them to be any particular value.
    28. Project Plan Effort (Hours/Days) – Duration => This is a calculated field [Baseline End Date – Baseine Start Date].
    29. Project Current Effort (Hours/Days) - Duration => This is a calculated field [Forecasted End Date – Actual Start Date].
    30. Link to Project Site (URL)
    31. Cost Variance (CV). This is a calculated field [CV = EV – AC]. A negative result means the project is over budget; a positive result means it is under budget.
    32. Schedule Variance (SV). This is a calculated field [SV = EV – PV]. Negative is behind schedule, Positive is ahead of schedule
    33. Cost Performance index (CPI). This is a calculated field [CPI = EV/AC]. We are getting $____ out of every $1
    34. Schedule Performance Index (SPI). This is a calculated field [SPI = EV/PV]. We are [only] progressing at ____% of the rate originally planned.
    35. Estimate at Completion (EAC). This is a calculated field [EAC = BAC/CPI]. As of now, how much do we expect the total project to cost?
    36. Estimate To Complete (ETC). This is a calculated field [ETC = EAC = AC]. How much more will the project cost?

    Product Team

     

    Page 1 of 1 (4 items) | RSS
    Bamboo Solutions Corporation, 2002-2010